Power update as of 12:55AM

Power Update


We regret to inform our MCOs in 2nd District that restoration works in Bobolosan Substation has been suspended and will resume early in the morning. 

Per info from our Technical Team naenergized an Power Transformer sa Bobolosan SS pero mababa an boltahe na nasulod based san record sa OCB. Nakipagcoordinate an NORSAMELCO Technical Team sa NGCP Calbayog ngan ginpa open san NGCP an breaker kay low voltage an kanra incoming current. Sa aga na magkokondukto inspection an NGCP san kanra Catarman-Laoang 69kV Line.

We are asking for your utmost understanding and patience on this matter. Thank you!

Ctto//Norsamelco







 